Sidewalk Rehabilitation Project - 2018

Project Description: This program includes the City's share of repair and replacement of cracked and deteriorated sidewalk segments identified and prioritized in the 2016 sidewalk survey. Each year, a scope of repair/replacement work will be scheduled based on funding availability and prioritization of needed repairs. The focus of FY 18‐19 will be completing the removal and replacement of approximately 300 locations previously identified through the sidewalk survey and coordination with utility companies to repair locations affected by their underground utility vaults and boxes.

Project Status: Design Phase 

Latest Update: 08/07/18. The design is 100% complete and the current focus is assembling all contract documents for the bid process.

Contact: Evelyn Moran, Assistant Engineer