Ocean Colony Pump Station Rehabilitation

Project Description: Replace 2,500 feet of sewer force main, rehabilitate existing pump station including new generator with sound enclosure, new pumps, new electrical, new redundant controls, rehabilitated wet well and manholes and a new flow meter.   

Project Status: Construction Underway!  Watch for Signage and Flagmen along Fairway Drive west of Greenbriar Road!

Funding Source(s): Sewer Enterprise Fund

Latest Update: 10/15/2020 - Ranger Pipelines Inc., is trenching and installing pipe along Fairway Drive . There will be occasional periods of one-way traffic along Fairway Drive west of Greenbriar Road which will be controlled by flagmen. One intersection with Fairway Place will remain open at all times during the workday and both Intersections will be open at evenings and weekends. 

Contact: Denice Hutten P.E., Associate Engineer, dhutten@hmbcity.com