Ocean Colony Pump Station Rehabilitation

OC ForceMain LINKS2Project Description: Replace 2,500 feet of sewer force main, rehabilitate existing pump station including new generator with sound enclosure, new pumps, new electrical, new redundant controls, rehabilitated wet well and manholes and a new flow meter.   

Project Status: Force Main Completed.  Construction continues at the Pump Station on Fairway Drive--Watch for Signage and Flagmen!

Funding Source(s): Sewer Enterprise Fund

Latest Update: 06/10/2021 - Ranger Pipelines Inc., has completed installation of the force main and has begun construction at the Pump Station on Fairway Drive. During the work at the pump station please expect occasional periods of one-way traffic at Fairway Drive near the Mullins Gate. The Mullins Gate will remain operational for two way traffic for Ocean Colony Association members. Project completion is anticipated September 15, 2021.  

Contact: Denice Hutten P.E., Associate Engineer, dhutten@hmbcity.com