Highway 1 Safety and Operational Improvements – North

Project Description: Operational and safety improvements to Highway 1 between North Main Street and Spindrift Way. Improvements include a Class I multi-use path (10-ft wide with two foot shoulders) from Main St to Spindrift Way on the East side of Highway 1, a new signalized intersection at Terrace Ave, four protected pedestrian crossings, local street connection to Frontage Rd/Terrace intersection, and improvements to bus stop pull-out areas.

Project Status:   Environmental clearance has been certified.  Coastal Development Permit has been issued.  100% design completed and submitted to Caltrans. Utility relocation/protection is being coordinated.  

Funding Source(s): Measure A grant from San Mateo County Transportation Authority (SMCTA) and Pacific Ridge Subdivision Traffic Impact Fees.  

Latest Update:  (3/15/2022)      100% design has been completed and submitted to Caltrans for their review and approval. Caltrans has been reviewing the latest revisions for final encroachment permit.  Utility relocations for gas line and electric poles are in design.   Right of way certification and utility relocations are expected by the end of 2022.   Regulatory permits to be obtained by 10/1/2022.  Agreement with SMCTA for construction funding to be executed in Summer 2022.  Construction is expected to start in 2023 and last approximately 18 months.

Contact: Ray Razavi, Transportation Engineer, E-mail

More Information:

HMB North Frontage Road South