PELICAN POINT GENERATOR REPLACEMENT  Project

Project Description: The project consists of removing and replacing the existing generator and automatic transfer switch, installing new conduit to the wet well, installing new phone conduit and other electrical improvements, installing new fence slats in the existing chain link fence and repairing and painting the electrical shed.  

Project completion anticipated in March 2022. 

Project Status: All permits have been received and the generator and transfer switch are installed and operational. The Contractor has minor finish work to complete the project. 

Funding Source(s): Sewer & Storm Drain Capital Improvements

Latest Update: 02-28-2022

Contact:
Denice Hutten, P.E., Associate Engineer
(650) 750-2005