PELICAN POINT GENERATOR REPLACEMENT  Project

Project Description: The project consists of removing and replacing the existing generator and automatic transfer switch, installing new conduit to the wet well, installing new phone conduit and other electrical improvements, installing new fence slats in the existing chain link fence and repairing and painting the electrical shed.  

Project completion anticipated in September 2021. 

Project Status: Under Contract.  Contractor has ordered the generator and has applied for required permits.  Potholing and site survey anticipated to begin last week of May.      

Funding Source(s): Sewer & Storm Drain Capital Improvements

Latest Update: 05-04-2021